Well, I just got back from MIT with my weekly quota of new ulcers, which I thought might interest you. We spent one day discussing the AS-204 situation, another on AS-501 and AS-502, and the third day primarily on crew procedures associated with the LEM lunar rendezvous crew timeline. I will give you my impression…
Category: AS-204 (Apollo 1)
Notes regarding the AS-207/208 Guidance Systems Operation Plan (GSOP) meeting with MIT
During the week of August 15, we held a review of the AS-207/208 Guidance Systems Operation Plan (GSOP) at MIT. Some things interested me which I will pass on to you here. I will also include some of the more significant decisions–that is, direction to MIT–that were made at that time….
In which is described the Apollo spacecraft computer programs currently being developed
It is possible to take advantage of the stretchout of the Apollo flight schedule in the manner in which we develop the spacecraft computer programs at MIT. Although the flight schedules have not been fixed, it is evident that certain things can be done which will not only improve the quality and capability of the…
Ground rules for MIT man loading for AGC programming
This is really for my own records, but in case you are interested, we presented the following ground rules to MIT with Bill Kelly’s (ASPO’s MIT Contractual Officer) concurrence. These ground rules were to cover the work they are doing in revising their man loading estimates for contract negotiations which are coming um in the…
Another Apollo spacecraft computer program status report
This is another of my gripping reports on the status of the Apollo spacecraft computer programs and associated matters based on my weekly visit to MIT on June 28 and 29….
Small program change needed in the AS-501/502 AGC program
In the course of development of the AS-206 computer program at MIT, a coding error was discovered which was immediately recognized as being common to the AS-204 and AS-501/502 programs. It is a scaling error, if you know what that means, which imposes the operational constraint of not operating one of the integration programs (i.e.,…
Another AGC program development report
Just got back from the northlands and couldn’t resist sending out another note, although I really don’t have much to report. The program development planning at MIT seems to be progressing nicely. We did pick up a couple of items that require attention; e.g.,…
Justification for SCAMA circuit to MIT/Boston
This memorandum is to provide justification for the addition of a SCAMA circuit between Houston and MIT/Boston and two additional telephones in Building 30, MSC….
Program Development Plans are coming!!
September 29th shall probably go down in history, at least in my diary, as the day of a major breakthrough at MIT. On that date we had an all day meeting attended by all key MIT management personnel involved in spacecraft computer program development. I expect it to be the first of similar weekly sessions…
AS-204 computer program status
During the week of July 4, 1966, the prime and backup crews for the AS204 mission attended briefings at MIT, which, among other things, led to their request that four changes be made in the spacecraft computer program for that mission. This request triggered off a considerable amount of activity which I would like to…